Selected Sewer & Water Experience


 

City of Cedar Rapids, Iowa

SANITARY SEWER IMPROVEMENTS MISCELLANEOUS FLOOD RELATED REPAIRS

Project Description: This project involved the repair of twelve flood-damaged sanitary sewer pipes in Cedar Rapids following the 2008 Flood. Pipes were evaluated and repair locations were determined from review of city-supplied sewer videos.

Two of the repairs required extensive coordination with business owners for determination of the exact location of the sewers underneath the owners' buildings. These two locations also required coordination and interpretation of specialized sewer service survey/internal tracer procedure to determine probable sewer service locations relative to the building structures and to the sewer main repair locations.

In addition to sewer repair, the project included pavement removal, pavement replacement, finish grading, seeding, and other restoration.

In order to expedite the repairs, the small project abbreviated bidding process was used, where possible. Funding for this project was provided by FEMA; therefore, project administration tasks included substantial coordination with FEMA to insure funding eligibility.

Project Cost: $250,000
Date Completed: 2008-2009 Construction

 


 

Ellis Boulevard NW Sanitary Sewer Improvements

City of Cedar Rapids , Iowa

Project Description: ANDERSON-BOGERT Engineers & Surveyors provided design of and project utility coordination for a sanitary sewer force main along Ellis Boulevard NW from Ellis Lane to 18th Street . This project was phase 3 of a multi-phase interceptor and force main improvements project downstream from the Morgan Creek lift station. The project consisted of parallel 18" and 24" force mains to serve the Morgan Creek lift station. Multiple lines were selected due to variable flow conditions (current and future), and to provide maintenance ability for very little extra initial cost. Included in this project were parkway improvements, such as islands and curb and gutter, for approximately 2,400 L.F. of Ellis Boulevard . Gravity sanitary sewer and water main were improved as well. The final element of this project was a recreational trail on the riverbank in Ellis Park. A portion of the force main runs under the trail alignment.

Owner: ................................................................... City of Cedar Rapids , Iowa
Owner's Representative: .................................... Mr. Dave Wallace, P.E., Eng. Dept.
Initial Schedule for Design: ................................. November 2003
Actual Time for Completion: .............................. April 15, 2004
(delay due to streets funding)
Project Construction Budget: ............................ $2,200,000.00
Final Construction Contract Amount: .............. $1,852,955.41


1st Avenue SE Water Main Replacements

Cedar Rapids , Iowa

Project Description: ANDERSON-BOGERT Engineers & Surveyors, Inc. completed the design of and provided construction observation for approximately 2,700 LF of 12" and 16" water main on 27th Street, 32nd Street, and 38th Street . These are all in older, urban neighborhoods with significant existing and abandoned utilities.

Owner: City of Cedar Rapids
Owner's Representative: Mr. Charles Saxton, Water Department
Cost of Construction: $360,000


Milburn Road Water Main Extension

Cedar Rapids , Iowa

Project Description: ANDERSON-BOGERT Engineers & Surveyors, Inc. completed the design of approximately 9,600 LF of 24" water main to extend from Blairs Ferry Road to West Mustang along Milburn Road .

Owner: City of Cedar Rapids
Owner's Representative: Mr. Bruce Jacobs, Water Department
Cost of Construction: $450,000


McCloud Run Sanitary Sewer Interceptor Study

City of Cedar Rapids , Iowa

Project Description: ANDERSON-BOGERT Engineers & Surveyors is currently completing a study of the McCloud Run Interceptor from 1st Avenue to 29th Street NE to 800 feet north of 42nd Street . The interceptor being studied includes approximately 980 feet of 42", 3120 feet of 36", 5400 feet of 30", 4965 feet of 21", 1600 feet of 18", and 1710 feet of 15" diameter pipe. The study area includes 5300 acres.

The goal of this study is as follows:

  • Determine what sections of interceptor are in need of improvement.
  • Provide a cost effective solution for providing additional sewer capacity in this drainage basin.
  • Identify C.I.P. projects for the improvements that are required.

Preliminary results indicate that the majority of the existing sewer is significantly under capacity for predicted future flow and that a replacement pipe is the most cost effective solution.

Owner: City of Cedar Rapids
Owner's Representative: Dave Wallace, P.E.
Cost of Study: $47,000

   


Sanitary Sewer Lines Study

City of Clarence , Iowa

Project Description: ANDERSON-BOGERT Engineers & Surveyors provided the coordination and supervision necessary for the smoke testing and televising of the city's sanitary sewer lines, analyzed the information gathered, and prepared a report for the IDNR.

Owner: City of Clarence
Owner's Representative: Michael Ellingson, Mayor
Cost of Construction: Not Applicable


2002 Miscellaneous Sanitary Sewer Improvements

City of Cedar Rapids , Iowa

Project Description: ANDERSON-BOGERT Engineers & Surveyors compiled flow data and tape review to determine the best design alternative to rehabilitate the lines at 25 sites. Two bid packages were prepared, one for lining and manhole rehabilitation, and one for reconstruction and point repairs.

Owner: City of Cedar Rapids
Owner's Representative: Dave Wallace, P.E.
Cost of Construction: $1,300,000 (original budget $1,700,000)

   


Industrial Park Improvements

City of Belle Plaine , Iowa

Project Description: ANDERSON-BOGERT Engineers & Surveyors completed the design of a 10" sanitary sewer extension and lift station and a 8" water main extension to the proposed Belle Plaine Industrial Park.

Owner: City of Belle Plaine
Owner's Representative: Tom Hollopeter, Mayor
Cost of Construction: $175,000
Financing: Sewer and Water Revenue Bonds


CDBG Lagoon Project

City of Clarence , Iowa

Project Description: ANDERSON-BOGERT Engineers & Surveyors designed a three cell lagoon to replace an existing mechanical treatment facility for municipal waste. This project included lift station, piping mains, and the lagoon structure. ANDERSON-BOGERT provided design, and construction staking and observation services.

Owner: City of Clarence
Owner's Representative: Mike Ellingson, Mayor
Cost of Construction: $725,000
Financing: CDBG